Ramping Up Construction At The Big Four Bridge

Friday, October 30, 2009 by Branden Klayko.
Big Four Bridge Construction Site

Big Four Bridge Construction Site



About two weeks ago, I had a chance to tour the construction site at the Big Four Bridge and snap a few photos of construction progress at the final phase of Waterfront Park.  Work has been moving along steadily, weather permitting, since these photos were taken, and additional pieces of the ramp structure have been lifted into place.


The day of my tour was cold and rainy, meaning the site was considerably muddy, but the sight of massive curving beams that form the approach to the pedestrian and bicycle crossing over the Ohio River to Jeffersonville was worth it.


An initial earthen mound forms the beginning of the elliptical spiral that ramps 60 feet into the air to meet the Big Four Bridge.  While the site was nearly abandoned on my visit, on a less rainy day, 25 to 50 workers would be seen preparing sections of the ramp.


Each of the four ramp sections and columns was manufactured in Tampa, Florida of steel that forms a naturally rusty finish meant to blend with the patina of the 1890s-era bridge.  The elliptical shape presented a challenge over what could have been a typical circular ramp.  Instead of one radius to conform to, the ramp contains seven radii.


Ramp sections consist of two parallel structural channels that are accessible for maintenance and repair work.  Small portals at each end will allow access into the dark and confined spaces.  Three cranes on site capable of lifting 100, 160, and 250 tons respectively have been used to hoist the steel into the air.  Each section rests on rubber pads on the piers and a central column will be filled with concrete to further secure the ramp.


A concrete deck wide enough to accommodate emergency vehicles will be poured on top of the steel structure leading to the bridge.  A 60-foot diameter platform sits at the base of the bridge and is sure to offer amazing views of the surrounding area when complete.


When funds are available, two I-beams will be installed on the Big Four Bridge and a concrete deck poured on top.  Existing wooden railroad ties and debris must first be cleared, but much has already been heavily damaged or destroyed in a fire on the bridge last year.  Stimulus funds are being sought to help pay for the Big Four decking and more details will be available in December.


You may also recall two proposals for installations on the Big Four Bridge site.  One plan calls for a $500,000 pavillion nestled under the bridge approach designed by architects DeLeon & Primmer of Shelby Street.  The pavilion is meant to draw attention to and honor the Hill sisters who wrote “Happy Birthday to You.”  At IdeaFestival 2008, Arne Quinze of Belgium proposed an intricate wooden lattice “cloud” weaving through the bridge over the Ohio River.  The plan called for interpretive stations detailing local history and even solar panels that would allow the cloud to glow and play music.




Big Four Bridge Construction Site

Big Four Bridge Construction Site


Construction at the Big Four Bridge

Construction at the Big Four Bridge





4 Comments. Now we're talking!
  1. Dave Morse

    November 1st, 2009

    9:17 am

    Thumb up 0

    Nice pictures! I hope they can work out a way to let people up on the completed sections of the bridge before it's all complete. That can only increase political pressure to get the whole thing built. People here don't 'get' the idea of a non-automotive bridge. Once they see and feel it for themselves, they're going to be gobsmacked.

  2. Diane

    November 2nd, 2009

    9:08 am

    Thumb up 0

    Yes, I agree, very cool pictures.

  3. JC

    November 2nd, 2009

    2:16 pm

    Thumb up 0

    I think "third phase" of Waterfront Park has a much better ring to it than the "final phase"? Biased.

  4. Branden Klayko

    November 13th, 2009

    7:27 pm

    Thumb up 0

    I agree, David. It’s going to be great to have a bridge dedicated solely to walking and biking. It should be a very peaceful route when it’s all done.

    JC, “third phase” does sound better than “final.” From here on out that’s how I will call it. Thanks for pointing that out.

Join the Discussion. Leave a Response.

The information in the form below is required, but, don't fret, we won't share your information with anyone. Sometimes our spam protection software freaks out when you put a link in the comments, so if you don't see your response immediately, know it's being held for moderation. You can write whatever you want, but please keep to civil discourse. Ad hominem attacks and other such boondoggery will be removed. If you have any questions, you may peruse our comment policy.

 

We Support

  • streetsblog.net
  • Urban Design Studio
  • Preservation Louisville
  • Coalition for the Advancement of Regional Transportation
  • Bicycling for Louisville
  • Bike Louisville

Facebook

brokensidewalk.com © 2010 Broken Sidewalk. All rights reserved. Terms of Service | Privacy Policy
For content usage questions, please review our Copyright Policy or contact bs [at] brokensidewalk [dot] com.
Creative Commons License